Goal Planning as of 12/7/04:

 

Timeline                      Action

 

12/1                             Turbine and associated parts arrived

 

12/1-12/27                   Finish rough program to account for 3 weeks

 

12/19                           Micro-hydro training in College Park, Maryland

 

12/27                           Leave US to Arrive in Dominica to start fieldwork

                                    Current program

 

12/28                           Begin installation

 

1/14                             Bring operations to conclusion.

 

Jan 16                         Return to the US.

 

Spring 2005              Report on events.  Continuously obtain flow measurements and             

                                  energy figures.  Plan for Spring Break trip to complete installation or           

                                  if completed, confirm everything is running smoothly.         

 

New Developments:

 

6 students and chair of Engineering reported to participate from EWB – Syracuse Chapter.

 

BBL revoked their commitment to donate pipe – EWB negotiating with President of Engineering for funding.  They are confident funding will be provided.

 

4 other UVM students interested in training.

 