Dominica Micro-Hydro Installation
Spring 2004 EE 186/195; By Alvin Chan and Adam Meil
*** BACKGROUND INFORMATION IS GIVEN AT THE END OF THE WEBSITE: WE BEGIN WITH WHAT HAS *** *** TAKEN PLACE SINCE THE FINAL PRESENTATIONS IN THE FALL OF 2004.
Training
Workshop
Electronic Load Governor (Closed)
Electronic Load Governor (Open)
Flagging at point of Foundation
Intake Tank - The water from in the intake tank is taken from naturally running water at a higher elevation. The entire water source is not nearly used completely
and there is no water shortage. The intake tank does allow a lot of water to flow out of it into the stream at all times. The hydroelectric complex
takes the water they need for use in the turbine and sends the rest back to the stream.
Water Pipe - This is the water pipe used by DOMLEC. It is 18" in diameter, yielding an extremely large potential flow.
Step Up Transformer - A wire from the generator first goes to a step up transformer to get the desired voltage, in this situation 11000 volts.
Old Trafalgar Turbine Unit & Valve Components - This is a picture of the original trafalgar turbine unit which was installed about 60 years ago and it looks very
similar to the unit that we are using, only on a larger scale. The valve components are very similar as well in this turbine. The main difference between
this system and the system that we installed is that our system had an ELG and this turbine used a (Mechanical) MLG.
Pressure Valve - From the pressure valve calculations as to how much power is being produced can be made. The idea is that the pressure valve stays the same
because of the load governor.
New Trafalgar Turbine Unit - This system was set up around 20 years ago and is well advanced from the previous system. The load governor is hydraulic and this
turbine unit is the one that is currently up and running at the hydroelectric complex. Again, this is very similar to the turbine that we are installing in
everything other than magnitude.
Control Room - This is the control room where troubleshooting and all that data is collected for the output of the turbine power. There was someone working in this room at all times sending and receiving data to the other DOMLEC power plants on the island.

Joint 1 - This is where the initial joint was, coming out of the intake tank. We felt that this was one of the most important points of the entire process because we had to put a joint in right away and there was a lot of instability here. We also needed to put a butterfly valve at this point so we could turn the water on and off as we pleased.
Intake & Joint 1 - In this picture you can see the intake tank and the pipe initially going out of the intake tank. It is clear to see in this picture that a maximum amount of flow through the 4 inch pipe is being used.
Joint 2 - This is about 1/3 of the way down the pipeline where there was a walkway crossing. We needed to dig to bury the pipe across the walkway and we needed two joints right after one another in order to run the pipe successfully. It is easy to see in the picture how supports were used and thrust blocks to keep the pipes stable under strenuous conditions.
Pipeline 1 - This is a picture of the pipeline 20' following the first joint. As is seen in the picture, the PVC pipe does bend some. This saved a lot of joints on the way down because the situation of having a straight pipe did not turn out to be ideal in this situation.
Turbine in House - In this picture Peter, a partner of ours, connects the valves of the turbine to the turbine inside the house.
Turbine Pipe Connection - This picture shows the pipe connected to the turbine. Note that the pipe does not go directly into the turbine. This was one of the biggest issues because we were unable to come up with a way to get the pipe to go straight into the turbine.
Clean Out & Flow - This picture shows the cleanout just prior to the foundation and also shows the flow at the bottom of the hill.
Pressure Gauge - Here the pressure gauge shows the pressure of the water through the 2 inch diameter pipe when the butterfly valve is opened at the intake tank.
ELG & Transformer Connected - This is the room after the ELG and transformer are connected.
Dump Load - Because all of the power from the turbine is not always needed a dump load has been set up. This is where extra power, governed by the ELG will be 'dumped'. The water will become very hot and is dangerous due to its high voltage.
Tasks for March, 2005: 1. Fix Final Pipe Joint - As can be seen in the picture, the final pipe joint is not attached properly and is very unstable. Upon returning we must make this final piece of the pipe stable.
2. Tighten Turbine Valves - As could be seen in the movie, there are leaks in valves of the turbine. These need to be sealed and taken care of so that a maximum flow can be taken by the turbine.
3. UV Paint - The PVC pipes that we used are exposed to sunlight and therefore will deteriate over time. Our plan is to paint them either with special UV paint or just to paint them a certain color in hopes of keeping them from deteriation.
4. Dump Load Consideration - The dump load does not necessarily need to be just wasted power. It could be used as a heating element for pretty much anything, perhaps a hot water heater in this situation.
A major component of this project was in the building of the foundation. There was no flat land near the foundation point so we needed to decide how to build a stable foundation that could protect against both weather damage and security dangers. We decided to design a foundation with 5' x 5' x 6" of concrete with steel beams around the edges. Then, using cinder blocks, making a "house" for the turbine and generator. This "house" was made with a hole for the pipe to connect to the turbine. The foundation took a lot of hard work and materials to build. The foundation was built at the bottom of the hill and all of the materials needed for building had to be carried down there. These materials included 2 tons of sand least 1 ton of stone aggregate, and about 1 hundred cinder blocks. The following pictures will take you through the process of building the foundation.
Information
Methods:
Final
Goal Planning/New Developments
Turbine Unit:
· SES - P175F (Specifications and cost)
· Site and Unit Specifications
Funding:
Invoice
from India (May have to save it to hard-drive first, then
open)
Final
Funding Report for Essentials
Funding
items unaccounted for thus far
Archives:
Developments from 10/19 –
11/30/04
Developments from 9/21 -
10/19/04:
· Goal Planning/New Developments
· Parts List with Prices from India
· URECA Application (Includes project overview and funding)
Pictures:
· Riverbed
· Partially Completed Intake Tank
Contact us Alvin: achan@emba.uvm.edu or
Adam: ameil@emba.uvm.edu